Pelican Amine-Treating Plant
PELICAN AMINE-TREATING PLANT
Client:
DT Midstream
Location:
Haynesville Shale
Project Summary:
Opero Energy designed and fabricated a 1,900-GPM amine-treating system for DT Midstream’s Pelican amine-treating plant serving the Gulf Coast region. The system was designed to treat 350 MMSCFD of high-CO2, high-H2S gas from the Haynesville Shale formation. The scope of work included engineering, modular process skid design, and in-house fabrication of all skids and system equipment. Opero Energy also supported the commissioning and start-up of the facility. The optimized anime-treating system effectively removes CO2 and H2S contaminants from the formation’s gas streams—allowing DT Midstream to meet pipeline specifications and focus on production from the Haynesville Shale.
Project Overview:
- Treatment for 350 MMSCFD of gas
- 1,900-GPM amine-treating unit
- 160-MMBTU/hr hot oil system
- Modular skids
Scope of Work:
- Engineering & design
- Fabrication & testing
- Commissioning & start-up support