PROJECT EXPERIENCE

Targa Resources Amine Treating Units

  1. Home
  2.  | 
  3. Project
  4.  | Targa Resources Amine Treating Units

BULL MOOSE AMINE TREATMENT

Williams Markham Gas-Processing Plant Expansion | Opero Energy

Client:

Targa Resources

Location:

Winkler County, Texas

Project summary:

Targa Resources contracted Opero Energy to address sour gas at the Bull Moose gas-processing facility in Winkler County, Texas. A custom-designed Amine-Treating unit was required to remove contaminants such as CO2 and H2S, including a complete gas-treating train and amine regeneration system. 

The Opero Energy team engineered, designed, and fabricated a complete modular gas-treating train and custom amine regeneration system, including efficient management of long-lead equipment to treat 850 MMSCFD of sour gas. The skid-mounted modular design integrated a 2,400-GPM amine circulation system and accounted for a future expansion to accommodate up to 4,800-GPM circulation. Our team will engage in on-site support for the commissioning of the equipment when the time comes. 

Our approach at Opero Energy focuses on quality and timely project execution, even when faced with challenges. In collaborating with Targa, we were able to deliver the full package on time while maintaining our sharp focus on qualityWe are thrilled to have been able to work with Targa Resources to provide a solution designed to their specifications and look forward to supporting them with the startup of the facility.

Thomas Guillot

Senior Project Manager, Opero Energy

Project overview:

  • 2,400-GPM amine circulation  
  • 4,800-GPM expansion potential 
  • 850-MMSCFD gas treatment 
  • 125-MMBTU/hr heating 

Scope of work:

  • Engineering + design
  • Procurement
  • Fabrication
  • Commissioning support

Have Questions? We Can Help.